Friday, 14 August 2009

Painting and friends

Thanks to Daniel, Sue and Fiona who came to help with various bits of painting during the week.
The shower is now grouted and ready for use

Monday, 10 August 2009

Monday-painting and tiling

The ensuite shower is now tiled - but not grouted and Daniel made a really good start on painting the walls in the bedroom. I'm quite proud of the tiling as it's the first tiling I've ever done. Chris did a fantastic job at cutting the holes in the tiles for the shower.

Friday, 24 July 2009

Ensuite

The en suite has been basically painted now.

Tuesday, 21 July 2009

Painting party no 1

For our first painting party in the loft we had a very special guest, Isaac came complete with Noise t shirt, ready to help. He also brought Mum and Dad with him and they helped out too! Many thanks as this means the loft has nearly all had its base coat now. Isaac did get a bit bored in the end and went off to watch the cricket.

Friday, 17 July 2009

week 18

This week the builders have finished the plastering in the loft room, I've started to prime the plaster surface and tonight (Friday) we will sleep there for the first time as we have my parents staying. The doors are on and I'm sure we will be cosy (if not very dark!)

Friday, 10 July 2009

Friday week 17

Nearly plastered, the en suite with all the suite in place but not plumbed in.

Friday week 17 - more plastering

The ceiling and most of the walls in the loft are now plastered.

Thursday, 9 July 2009

Thursday week 17- plasterboard

Our bedroom now has walls all round it and they are all plasterboarded.

Wednesday, 8 July 2009

Wednesday week 17

The last of the dividing walls have gone up in the loft room and the last wall in the ensuite has been plastered now.

Tuesday, 7 July 2009

Sunset photo no 1

Obviously one of the main reasons for wanting to build a loft conversion was to get better photos of the stunning sunsets which we could see through the gaps in the houses behind us. Tonight gave me my first opportunity to take a photo from the loft room. Not the best sunset but it shows me the view!

To see the photo bigger click on it.

Friday, 3 July 2009

Plastered- partly again

The ensuite bathroom in the loft has now been plastered with the exception of one wall, and the main loft room has the big wall plastered as well.

Thursday, 2 July 2009

Walls going up inside.

The loft room and its en suite is really starting to take shape. The walls of the ensuite are now up, Rebekah has had a go at "showering" and it is ready to start plastering hopefully tomorrow.

Saturday, 27 June 2009

Friday week 15

The ceiling now has plasterboard over most of it.
Next week, internal walls.

Friday, 26 June 2009

Thursday week 15

Insulation covered by more insulation in the loft!!!

Wednesday, 24 June 2009

Tuesday, 23 June 2009

Tuesday week 15

When the builders turned up this morning with LOADS of dust sheets I was rather concerned. I decided they were obviously going to knock holes in the ceiling. I was right!!!! They've also removed the cupboard at the top of the stairs (and put something there to stop the children falling down the stairs in the night!). Lots of noise and dust followed but the builders have done a great job of clearing up after themselves.
The roof has also had lots going on today. The tiles have nearly finished going onto the dormer and the ridge tiles are also almost complete.
The other thing they have done today is to start on the insulation in the loft room and the shape of the ceiling there. It's all starting to take shape.

Monday, 22 June 2009

Monday Week 15

It's now possible to see the shape of the ensuite

Thursday, 18 June 2009

Thursday week 14

The wiring for the lighting ring and the socket ring today

Wednesday, 17 June 2009

Wednesday week 14

All starting to take shape